Which factor is NOT typically included in a rigging plan?

Prepare for the NLC Electrical Grid (eGRID) and Rigging 2 Test with our comprehensive study resources. Utilize flashcards and multiple choice questions complete with hints and explanations to excel in your exam!

A rigging plan is a critical document created to ensure the safe and efficient execution of lifting and moving operations. It includes various elements essential for the success of the operation.

Load specifications are fundamental; they provide detailed information about the weight and shape of the load, allowing the riggers to select appropriate equipment and techniques for the lift. This ensures that the rigging setup is capable of handling the load without risk of failure.

Personnel assignments are also a key component of the rigging plan. This specifies who will be responsible for each aspect of the operation, ensuring clear communication and accountability. Properly assigning roles is vital for the safety of the crew and the success of the operation.

Equipment lists are necessary to outline all tools and rigging gear needed for the lift. This inventory ensures that all required equipment is on site and in proper working condition, minimizing the risk of accidents due to equipment failure or mismanagement.

While weather forecasts can impact rigging operations, they are not typically considered a core factor within a rigging plan itself. Instead, they are taken into account as a separate consideration when planning the lift, as adverse weather can affect safety. Thus, while knowing the weather is important, it is not a standard element included in the rigging plan